The C3+ Fractionation Plant consists of the following process sections: C3+ feed surge drum to stabilize and remove any dissolved gases in the feed, a De-ethanizer, De-propanizer, De-butanizer, C3 Stripper and C3 Splitter to separate the different products and Propane refrigeration section to supply external refrigeration for the columns. Additionally, the C3+ Fractionation Plant will have a hydrogenation section.

ClientArya Sasol Company
StatusFinished
Duration50 Days
ServiceBasic Design
BusinessPetrochemical
Capacity
Polymer grade Propylene:35000  Ton per year
Propane:6000 Ton per year
C4 Cut:65000  Ton per year
C5+:60000  Ton per year
LocationArya Sasol Petrochemcial Complex (Assaluyeh)