Project Information

Water Optimization study, Plant survey and study documentation for raw water treating, Circulating water system, waste water treating, fire water pumping station and network condensate recovery and BFW supply power plant condensate polishing, sewerage system and sour water and spent caustic. the activities to be performed are Plant Survey, Optimization, Basic Design and Engineering, new equipment selection, Sizing and modification of the existing equipment

ClientHOMS Refinery Company
StatusCompleted 
Duration7 Monthes (2004-2005)
ServiceEngineering
BusinessOil Refinery
Capacity 
LocationHOMS, Syria